Bucko Mill

Rockcliff controls a 7-year processing lease of the Bucko Mill and tailing storage facilities at the Bucko Lake Mine from CANickel Mining Limited near Wabowden, central Manitoba. The mill, initially designed for nickel, would be re-developed into a copper processing mill by Rockcliff Metals in the short term.

In Q2 2020, Rockcliff will complete metallurgical optimization studies to establish required design change to convert the mill into a copper processor. By Q3 2020, the Company aims to complete establishing cost of conversion to copper processor and make production decision. 

  • Projected Timeline
    Q2 2020
    Complete metallurgical optimization studies for mill changes
    Q3 2020
    Establish cost of conversion